TurnoutsMainlineBC
CN Rail British Columbia
Upgraded two mainline turnouts for CN Rail.
Removed existing turnouts and installed new #12 136RE turnouts.
One located in Chetwyn and the second in Fort Saint John.
Hired a local construction company to assist with grading, moving turnouts, and spreading ballast.
Utilized local workforce when available and utilized local motels and restaurants with our out-of-town personnel.
Work completed on time and within budgeted value.
Project StatusCompleted
Value
$250K
Turnouts
2 upgraded
Locations
Chetwynd & Fort St. John
Project Date
December 08, 2023